This week, the carpenter promised the apertures will be fitted in and the house can finally start getting cleaned up. Kitchen and bathroom can then be safely installed. I cannot risk a similar incident happening as happened recently, so security is one issue I'm keen on.
We had the usual end of August torrential rain this week and thankfully I was there to keep the water from making its way into the hall downstairs. The glass ceiling for the courtyard is nowhere in sight and so I have asked the supplier to fit in a temporary plastic one until the real one arrives from Germany. That should take care of any other showers.
I also checked the roof after the downpour and noticed a small puddle had appeared by the door of the roof garden. The tiler has been asked to come again and take out two/four of the tiles and lay them again so that no water puddle remains.